August 2021

Location: Winnipeg, Manitoba

Project Goal:

The goal is to dismantle the huge boiler in order to make space for the new generators.

Scope:

Rakowski provided asbestos abatement, boiler torching, as well as hauling of metal pieces. One person was assigned to torch the boiler, 6 men for asbestos abatement, and two men to move the metal closer to the door with mini excavator.

Number of Crew Involved with the Project:

9 men

Duration:

7 Days to complete.