March 2022Location: Borden, Saskatchewan
Project Goal:
The goal for the job was to dismantle and remove old truss sections of the CN Train Bridge and replace it with new ones.
Scope:
PCL Construction lowered truss sections to the ground so our team can cut them apart and get the dismantled material ready for transportation.
Number of Crew Involved with the Project:
6 men
Duration:
21 days, from start to finish.